Nevada Geothermal Power reports on progress for Blue Mountain Plant

Nevada Geothermal Power Inc. update on the construction and operations activities at its Blue Mountain ‘Faulkner 1’ 49.5 megawatt (MW) (gross) binary cycle geothermal power plant.

In a recent company statement, Nevada Geothermal Power Inc. (TSX-V:NGP) provides an update on the construction and operations activities at its Blue Mountain ‘Faulkner 1’ 49.5 megawatt (MW) (gross) binary cycle geothermal power plant.

In the report, the company states that it “has entered into a Procurement and Construction agreement with Industrial Builders Inc. to perform turnkey construction services for a geothermal fluid gathering and re-injection system (pipeline) connecting to the Power Plant, and production and injection wells.

The agreement includes the procurement of materials and equipment, construction, testing and supervision of testing. Pipeline foundation work has begun and the start of running the pipeline installation will commence later this week.”

In addition, the company provides the “following status updates:

NGP has completed three successful injector wells (58-15, 58A-15 and recently completed 57-15) and is presently drilling deep well 61-22. Thereafter an additional shallow injection well will be drilled. Well field completion is within the critical timeline for plant testing.”

Source: Company statement via MarketWire